AEMO wants ‘demand response’ as strategic reserve

You will recall that after the closing of Hazelwood Power Station at the end of March 2017 fears were held that the 2017-18 summer would see extensive blackouts. AEMO, the Australian Energy Market Operator, was tasked to assemble a strategic reserve to keep the lights on.

AEMO assembled a reserve of 1150 megawatts mainly “demand response” capacity with capital cost approaching zero, but the mechanism the agency had used called the Reliability and Reserve Trader or RERT, can’t be automatically rolled over for the summer of 2018-19. And perhaps it can’t be done at all, because the rule-maker, the Australian Energy Market Commission, has changed the rules governing the RERT so that the mechanism can only be used on 10 weeks notice in an emergency as a last resort, which is simply impractical.